Indian Railways Approves Projects worth ₹1,236 Crore for Upgradation

Newzville
4 Min Read

NewzVille Desk

Indian Railways has approved projects worth approximately ₹1,236 crore aimed at significantly upgrading its communication backbone and expanding the Kavach automatic train protection system across multiple zones. These approvals cover three separate proposals. Two are focused on optical fibre and ground wire infrastructure on Central and Western Railways, and one on deployment of Kavach on high-utilisation routes of Southern Railway.

Central Railway Gets Upgraded Fibre Network: ₹623.63 Crore

Two complementary works have been approved to build a robust, dual-path communication backbone across Central Railway’s network, covering all five of its divisions — Solapur, Nagpur, Pune, Bhusawal, and Mumbai.

First, a special type of composite overhead wire called OPGW (96 fibre) will be installed along the existing 25 KV electric traction lines on 2,250.68 Rkm, covering Solapur, Nagpur, Pune, and Bhusawal Divisions. This wire does two jobs at once: it acts as an earth protection wire for the traction system and also carries optical fibre for communication. Since it runs on the existing traction towers, no new civil infrastructure is needed. Cost: ₹238.9363 Crore.

Second, underground optical fibre cables (2×48 fibre) will be laid on one side of the track over 2,673.21 Rkm across all five divisions — Solapur, Pune, Nagpur, Bhusawal, and Mumbai. Together with the OPGW on the other side, this creates two independent fibre paths on every route, ensuring the communication network stays operational even if one path fails. Cost: ₹384.6887 Crore.

The additional fibre capacity will also be leased out as dark fibre, generating revenue for Indian Railways.

Kavach Safety System Extended to 548 km on Southern Railway: ₹310.18 Crore

Kavach is Indian Railways’ automatic train protection system that prevents collisions by automatically applying brakes if two trains are on a collision course or if a signal is passed at danger. Under this approval, it will be deployed on high-traffic routes across Tamil Nadu, Kerala, and Karnataka.

Under this approval, Kavach version 4.0 will be deployed on two sections of Southern Railway:

Jolarpettai–Erode (180 Rkm, Salem Division) and Chennai Beach – Tambaram – Chengalpattu (60 km, Chennai Division) — along with new optical fibre cabling. Cost: ₹158.74 Crore.

Shoranur–Mangalore (308 km, Palakkad Division) — along with new 4×48 fibre OFC cabling. Cost: ₹151.44 Crore.

These works are part of Southern Railway’s sub-umbrella project worth ₹2,950 Crore.

Western Railway to Complete Fibre Backbone for Rajkot and Bhavnagar Divisions at ₹302.2589 Crore

Optical fibre cables (2×48 fibre, on each side of track) will be laid on the remaining stretches of two Western Railway divisions in Gujarat — 1,064 km in Rajkot Division and 589 km in Bhavnagar Division, totalling 1,653 km. This fills the last gaps in the fibre communication network of these divisions.

A strong fibre backbone is essential for Kavach and LTE-based train control systems to function reliably. Completing this network ensures Western Railway’s Kavach rollout can move forward without delays. These works are part of Western Railway’s sub-umbrella project worth ₹2,800 Crore.

Share This Article
Follow:
Founded in 2024, NewzVille has got some name and fame. With more than 28 years of long journalistic career, the Editor-in-Chief had remained in various key positions at News Today Pvt Ltd, ETV Networks, Lok Sabha TV, Rajya Sabha TV, and Sansad TV. As an accredited Video Journalist for more than 17 years under Ministry of Information &Broadasting, Government of India covered State Visits of Prime Minister and Vice President. With coverage spanning 2 General Elections and more than 18 Assembly Elections, notable work includes national security series, live chamber telecasts, and audience-favorite documentaries. Key interests remain in Documentaries on Armed Forces and Travelogues.
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *